Utility relocations to begin for FM 518

Date:

by Nicole Bradford

The widening of FM 518 from Old Chocolate Bayou and McLean inched closer to reality this month as city leaders approved a contract to relocate utilities. 

City Council on Jan. 13 approved an engineering contract with Cobb, Fendley & Associates for utility relocation, a process that typically takes about a year. The FM 518 widening is set to go out for construction bids in 2027. 

“TxDOT is covering 100 percent of the road construction, and then we’re responsible for the utility relocation where we have utilities in their right of way,” City Manager Trent Epperson told council members. 

The Pearland Economic Development Corp will reimburse the city’s portion of contract costs. 

The project calls for widening the road from four to six lanes, with wider outside travel lanes designed to accommodate bicycle traffic, a raised median, and outside pedestrian sidewalks, according to TxDOT plans. 

Staff Report

Popular

More like this
Related

Friendswood residents have until June 30 to weigh in on proposed bond projects

Time is running out for Friendswood residents who want...

Student wins 1st place at International HOSA Conference

Friendswood High School student Vikram Gupta has earned international...

Superintendents to unite for community youth bash

Students and families from across the Pearland and Alvin...

Mental health among June school board topics

Stating the importance of mental health support, Pearland ISD...