City: Natatorium work on schedule

Date:

Major repairs and replacements at the Pearland natatorium are on schedule despite the impacts of Hurricane Beryl, according to the city.

The natatorium project began July 1 and is expected to continue through Sept. 22. The natatorium is closed since pools must be drained. Work includes replastering the competition pool and replacing the air handling unit, chemical treatment system, ultraviolet sanitation system, and mechanical filtration system.

A grand reopening of the natatorium is planned for late September or early October.

Staff Report

Popular

More like this
Related

Wiltz Wins Pearland Mayoral Race; Incumbents Hold Council and School Board Seats

Pearland voters elected a new mayor while largely maintaining...

Voters Approve 3 of 4 FISD Bonds, Reject Westwood Elementary

Voters in Friendswood ISD approved three of four bond...

Friendswood City Election Results

Voters in Friendswood returned one incumbent to City Council...

PISD board: Workshop needed for library book questions

After another school board meeting became mired in library...